From:
wolfe@PSFC.MIT.EDU
Reply-To: WOLFE@PSFC.MIT.EDU
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator
C-Mod Weekly Highlights
Dec 30, 2002
The maintenance
period continued at Alcator C-Mod last week.
ICRF Systems
------------
FMIT#4
was retuned to 78 MHz from 70 MHz. Into
dummy load, 1 sec
pulses up to 1.1 MW were completed. Further refinement of the tune is
required
for higher power pulses.
Following removal of all the antennas, an
initial inspection showed that the
modifications to the antennas prior to
the 2002 campaign were successful.
Modifications to shield the BN-metal
interfaces from the plasma were
successful on all antennas. No melt damage on plasma facing elements
was
found except for a few washers on D and E-port antennas. The reason for the
minor melt damage to
these few washers is unclear. The
modifications to the
J-port current strap also appear to be
successful. No arc damage was found
at
the "bridge" location.
The J-port maximum voltage
obtained in this campaign exceeded the
previous limit by ~15%. The
maximum
voltage limitation on all antennas appears to be related again to
where E
parallel to B. For the D
and E-port antenna, the voltage limit was ~10% lower
than in past years. The modifications made to the FS to shield
the BN-metal
interface resulted in an increased electrical length of the
antenna. This
changed the voltage
pattern in the transmission line and placed a higher
voltage in a 20 ohm
section of the vacuum transmission line.
We are currently
considering modifying this section of line to 50
ohms. Initial analysis
suggests
this would increase the voltage handling of this line section.
J-port also
had similar damage at a low impedance section of the vacuum
transmission
line. At the transition from coax to
parallel plate transmission
line, a low impedance coaxial section had arc
damage where E is parallel to B.
We are considering modifying this line
section to ~50 ohms as well. The
most
notable failure were the top and bottom end tiles. A total of four tiles
failed. The likely explaination is the disruption
induced rocking of the
fastener assembly.
As been reported earlier, a new tile design has been
completed and
is undergoing testing.
DNB Systems
-----------
During
the week of 23 Dec, plans for redesigning and fabricating
replacements for
two damaged MSE mirrors have been finalized.
The new
design will use stainless steel clamps to hold the mirrors
down over nearly
their entire perimeters (with a break to eliminate
disruption eddy
currents). Teflon
gaskets will be inserted (and trapped) on all edge
surfaces to pad the
contact between the stainless steel and the glass.
This design requires
shrinking the mirrors by about 0.5 cm on all edges.
To save time and money,
we will use spare mirrors that already have
dielectric coatings, and cut
off their edges, rather than buying and
coating new blanks. The new mirrors and mounts will be subjected
to
appropriate shake tests.