From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject:  Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Organization: MIT


               Alcator C-Mod Weekly Highlights
                       Jan 13, 2003


The Alcator C-Mod maintenance period continued last week.  Work on
machine instrumentation, ICRF systems, Lower Hybrid MIE Project, and
diagnostics progressed.


Operations
----------
                          
We continued to work on upgrades to the TF voltage tap, thermocouple, and
heater leads.  We are approximately 70% done with this project.

A conceptual design for a set of field correction coils has been developed.
It is believed that non-axisymmetric error fields may have affected plasma
performance during high current operation in the last campaign. A set of
coils to be mounted on the igloo structure is proposed to address this issue.


ICRF Systems
------------

The placement of the current probes on the D and E Port antennas is
being optimized using our rf simulation software.  These probes are
used to sense faults during operation.  A problem with the motorized
13.8 kV switch in the high yard has been identified and repairs are
progressing.


Lower Hybrid MIE Project
------------------------

Work continued on the new SFOL design.  The Low Power Microwave rack
SFOL receiver chassis assembly, including the wiring, is complete.
The Low Power Microwave rack SFOL transmitter chassis assembly is near
completion and the parts arrived to finish the I-Q detector wiring
inside the chassis.  Five DFOLs for LH system controls have been
successfully tested.  We continue to specify and procure cabling for
the low power microwave rack and interconnections to the launcher.

A temporary pump has been installed in the Lower Hybrid water cooling
system while warranty work is being performed on the primary pumps.
This pump will allow full power tests of the klystrons to be made with
the HVPS.


MSE Diagnostic
--------------

Work continues at PPPL and MIT on developing two approaches for
disruption-resilient mirrors for the C-Mod Motional Start Effect (MSE)
diagnostic.  An approach based on existing spare glass (Vycor) mirrors
will use a stainless-steel rib structure that supports the mirror
along its entire periphery, and 0.040" Teflon cushioning between all
glass and metal surfaces.  The design of this approach is complete and
fabrication of test components has started.

An alternate design is based on a metallic substrate, Inconel
625, coated with silver and overcoated with a dielectric for
protection against oxidation.  A mechanical design has been completed
that reduces disruption forces by removing most of the Inconel
substrate from the rear of the mirror.

At the present time both designs are being carried along in parallel.


Travel and Visits
-----------------

Monty Grimes was at AFT in Germany last week reviewing progress on the
Lower Hybrid MIE Project circulators.