From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Approved: plasma@cs.uml.edu
Alcator C-Mod
Weekly Highlights
February 21, 2003
On
February 20 and 21 a meeting of the Alcator C-Mod Program Advisory
Committee
was held at MIT. Work continued
invessel on diagnostics and
instrumentation. Fabrication and installation of control coils also
continued. Work on the lower hybrid launcher is
proceeding well at
PPPL.
Physics
-------
A
meeting of the Alcator C-Mod Program Advisory Committee was held at
MIT on
Thursday and Friday of this week. The
committee members are:
Vincent Chan (GA), Tony Leonard (GA), Dick
Majeski (PPPL), Mike Mauel
(Columbia, chair), John Sarff (U. Wisc), Alan
Sykes (UKAEA), Yuichi
Takase (U. Tokyo), and George Tynan (UCSD).
All
eight members of the committee attended the meeting. Rostom Dagazian
attended from DoE.
Presentations
were given by the Alcator C-Mod Group on the current
status of our
research and plans for the next five years.
These
presentations can be found at
http://www.psfc.mit.edu/cmod/sciprogram/Cmod_PAC_2003.html
The
committee was asked to provide feedback and guidance on our
proposed five
year program, including the goals and priorities, in the
context of
C-Mod's place in the national and international magnetic
fusion
programs. They were also asked to
provide feedback on how best
to present our program in light of our
upcoming review.
Following the presentations, the committee gave
their initial verbal
feedback to the group. Written recommendations will be given to
Miklos Porkolab and
Ian Hutchinson shortly.
Operations
----------
The
invessel E-Port antenna installation is complete except for the BN
tiles
which will be installed just before pumpdown.
The new J-Port
antenna back plate has been machined and has been
sent out for
plating.
Five of the eight control coils are
complete. Winding has begun on
the
sixth. Documentation of the power
supply and the in cell
connections for the new control coils is underway.
All materials are
in house for the control coil patch panels with
fabrication to begin
soon.
Lower Hybrid MIE Project
------------------------
By
this Friday, all major components for the LHCD launcher had been
been
received at PPPL. Recent deliveries
included all high power
phase shifters, rear waveguide assemblies, and
standard waveguide
component loops.
The last component (protective tile assembly) will
be delivered the
first week of March. Work is
progressing on
installing the launcher vacuum assembly on the vacuum test
stand.
Vacuum testing is expected to be performed early March. RF testing of
the rear waveguide
assembly will begin next week.
At MIT, the dummy load has been
brought back online and 50 kV tests of
the HVPS and crowbar were completed
successfully. Some overcurrent
trips
have been detected and are being debugged.
Work on the fixture
to mount the first circulator is well
underway. The ethernet fiber
optic
lines to the three cart equipment racks are operational. The
data acquisition racks will be
installed within the next few days.
Work also continued on the active
controller software.
Details of the Lower Hybrid CAMAC timing system
are being worked out.
IDL programs for the operator interface to the
timing system are being
developed.
Parts of the DNB timing program will be used as a model
for this
system. Don Patterson, UT, who
developed the DNB software is
helping out with this process.
Travel
and Visits
-----------------
Ned Sauthoff and Gerd Schilling,
both from PPPL, attended the C-Mod
PAC meeting. Gerd Schilling presented the PPPL collaboration's
contributions
to the C-Mod program and participated in programmatic
discussions.
Bill
Rowan, UT, was also at MIT this week and attended the PAC meeting.