From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Alcator C-Mod Weekly Highlights
February 28, 2003
Work continued on invessel
installations, the Lower Hybrid MIE Project, and
ICRF systems. Upgrades to the data system are
proceeding.
Physics
-------
Based on an
extensive database developed from discharges between 1996
and 1999, a
strong correlation has been established between the plasma
stored energy
increase (normalized to the plasma current) and the core
toroidal rotation
velocity increase after the H-mode transition for both
ICRF and Ohmic
plasmas with no external momentum input. The rotation
velocities during
the 2002 campaign are 20 to 30% higher for a given stored
energy increase
compared to the established trend. Unless the discharge
characteristics
have recently changed, it appears that in 2002 the plasma
stored energy as
measured by the magnetics is being underestimated by
this same amount,
consistent with independent kinetic-magnetic comparisons.
Since the
rotation database involves changes in the stored energy after
the H-mode
transition, it is implied that the stored energy is
underestimated by a
scale factor, and not an offset.
Operations
----------
On
Friday the entire C-Mod data archive was relocated to a linux
server. In
addition, all of our CAMAC serial highways have been moved
from an OpenVMS
server to a linux server. Everyone has
been
encouraged to begin testing their data acquisition systems and
analysis
programs to make sure they are linux compatible as soon as
possible.
During the next few weeks, we will fully test the C-Mod data
acquisition
system including the operator machine cycle applications,
shot cycle
announcement system, and the plasma control system console
(PCS) in
preparations for the next C-Mod run campaign.
We continue
installation of the new control coils.
Six out of eight
coils are now installed on the igloo.
ICRF
Systems
------------
D-Port antenna feedthroughs and antenna
straps have been installed
invessel (E-Port installation was completed
last week). The J-Port
support
plate has been copper plated and baked and will be installed
invessel next
week.
We continue work on transmitter control and protection
system
upgrades.
LH MIE Project
--------------
At
PPPL, the LHCD high power phase shifters have been tested
successfully for
VSWR and phase delay. The standard
waveguide loops
are also being checked.
Removal of braze material from the vacuum
side around the ceramic
windows of the antenna front end is now 75%
complete. Alignment of the port extension has been
completed, and the
vacuum waveguide assembly will be inserted prior to
test stand
installation.
At MIT, work continued on the amplitude and phase control
system.
The HVPS and crowbar tests into the dummy load are complete, and
high
power testing of the klystrons will begin next week.
Diagnostics
-----------
Significant
progress was realized this week at MIT on component
fabrication and
testing for the upgraded MSE glass mirror system.
Outside vendors
delivered four of six required pieces of the mounting
hardware, with
delivery of the final two pieces expected next week.
We successfully
completed final cutting of two replacement mirrors on
a waterjet, as well
as four test glass blanks and two test backplates
for shake testing.
Travel
and Visits
-----------------
Miklos Porkolab attended the VLT
PAC meeting in San Diego. This was his
last attendance, MIT will be
represented by Jeff Freidberg in the
future. Jeff has also taken on the
role of VLT PAC Chair.
Earl Marmar attended the meeting of the Next
Step Options Program
Advisory Committee held at General Atomics in San
Diego.