From: irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma


               Alcator C-Mod Weekly Highlights
                      March 7, 2003


We continue to complete invessel work in preparation for pumpdown.
Work also continues on ICRF and Lower Hybrid MIE Project systems.
Machine instrumentation is being brought back on-line.


Physics
-------

Stewart Zweben, PPPL, gave a talk at the C-Mod physics meeting on edge
minority heating for H-mode control.  This talk described how minority
heating near the edge of C-Mod plasmas might be used to generate fast
ion loss and so control the edge radial electric field and the H-mode
transition.  Topics discussed were: previous work, edge resonance
conditions, tentative experimental plans, diagnostics and analysis.
Initial simulations of Er by C. S. Chang were also discussed.


Operations
----------

Work has concentrated on invessel work this week as we approach
pumpdown.  The J-Port horizontal flange has been reinstalled and
installation of the antenna will begin as soon as all the rf vacuum
feedthroughs are installed and leakchecked.  We continued work on the
MHD antenna, glow discharge cables, invessel alignments, and
installation and testing of invessel cabling.  The machining of the
new BN tiles for the J-Port antenna has been completed.

We continue the migration from VMS based to linux based data
acquisition software.  Data system diagnostic routines used on the VMS
based system now work under linux.  Data highways and user software
are being tested and prepared for full data acquisition shot cycle
tests.

Machine instrumentation is coming back on-line in preparation for pumpdown,
vessel bake, cooldown, and ECDC.  Machine information is again being
trended to the MDSplus tree.


Lower Hybrid MIE Project
------------------------

At MIT, we continue to bring transmitter protection and control
systems on-line in preparation for high power klystron tests.  The data
acquisition equipment and software have been tested successfully.  More
parts for the active controller equipment chassis have been ordered,
as backplanes for the chassis are being populated.

At PPPL, cleaning of the LHCD coupler ceramic vacuum windows has been
completed, and the inner metallic surfaces are now being copper
plated.  The vacuum waveguide assembly has been successfully inserted
into the port extension for a trial fit-up. More polishing of the
launcher rails is needed for a smoother surface finish and an easier
movement of the launcher.  Mounting of standard waveguide components
onto the rear waveguide assembly has started.


ICRF Systems
------------

The process of developing a detailed cost and schedule plan for the
fast ferrite tuner project has begun. Based on response time and
required magnetic field, preliminary specifications for the power
supply for the electromagnet have been developed.  Measurements of the
ferrite losses are underway.


MSE Diagnostic
--------------

All fabricated components for the refurbished Motional Stark Effect
diagnostic have been received at MIT.  Shake testing of the new mirror
support frame has confirmed that the mirror is now capable of
surviving accelerations of 1700 g in both the longitudinal and
out-of-plane directions, which far exceeds the expected
disruption-induced accelerations.  Final vacuum baking of several
components will take place over the weekend.  Final assembly,
installation, and alignment will be performed on Monday, in
anticipation of close-up of C-Mod mid-week.

The INCONEL 600 backup metal mirrors for the MSE diagnostic are
in-process at PPPL.  Once machining operations are completed at PPPL,
the mirrors will be sent to one vendor for polishing and then to a
second vendor to be coated.


Travel and Visits
-----------------

Martin Greenwald and Miklos Porkolab traveled to Washington DC to
attend a meeting of the Fusion Energy and Science Advisory Committee.
The principal issues at the meeting were a discussion of the 2004
budget, US ITER participation, and the 35 year development plan.