From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod Weekly Highlights
March 28, 2003
Purging of the cryostat
has begun in preparation for cooldown of the
machine which is expected to
begin early next week. Testing of
the
control coil prototype has been completed under hybrid control. Work
proceeded on ICRF and Lower Hybrid
systems.
Operations
----------
The C-Mod shot
cycle has been ported to linux in preparation for the
start of the next
campaign. This port includes the
automated
announcement system, the bigboard, and the action monitor. Cycle
tests of the full data system
were also completed successfully this
week. The hybrid computer has been used to pulse the prototype
control
coil and stray field measurements have been made around and
inside the
magnetic shield designed to protect the pumping station
turbo pumps. Tests of the machine mounted control coils
is expected
to begin next week.
Cabling to the coils, the coil patch panel, and
coil case grounds
were installed this week.
Installation of the new LN2 sump was
completed on Friday and a GN2
purge of the cryostat was begun. Moisture levels below 200
parts/million
are required before LN2 can be added to the sump, and
cooling of the
machine can begin.
The flywheel inspection is going well. The tomographic ultrasound
test of the
flywheel was begun on Thursday. We
expect the inspection
to be completed mid next week.
ICRF
Systems
------------
We continued to re-install transmission
line components, DC breaks,
and other hardware required to supply power to
the antennas. The #1
and #2
transmitters have been brought back on-line at the 1.5 MW level
into a
dummy load. The #3 and #4 transmitters
should become
operational next week.
Design work continues on the fast ferrite
tuner.
Lower Hybrid MIE Project
------------------------
At
MIT, approximately 75 kW (of an eventual 250 kW) has been delivered
from a
klystron into a dummy load for the first time using the HVPS.
The voltage
from the supply was limited to 40 kV as we verify and
debug
instrumentation.
At PPPL, very good progress has been made on the LH
launcher. The
rear waveguide
section is almost assembled, with supports, loads, and
patch panel
connections to couplers, among other components, also
being
installed. The support/sliding
structure for the front shroud
assembly has been checked out with
temporary hardened steel rails. The
launcher successfully passed its leak
check on the vacuum test stand.
Stellite bearing surfaces are being
prepared for replacement of the
steel, after which the tests will be
repeated before delivery to
MIT. The front couplers have been completed
and are now being leak
checked prior to installation on the shroud
assembly.