From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod Weekly Highlights
April 4, 2003
The Alcator C-Mod vacuum
vessel is currently under bake at 120C.
Work
continues on the new non-axisymmetric control coils, Lower
Hybrid
Project, and ICRF systems.
The flywheel inspection has been
completed.
Operations
----------
The
flywheel inspection was completed successfully on Wednesday.
A tomographic
UT inspection of the flywheel rotor was done.
The
bearings were checked using dye penetrant, magnetic particle,
and UT
techniques. Re-assembly of
the flywheel is underway.
A bake of the Alcator C-Mod vacuum vessel
was begun on Wednesday. The
bake
is expected to last until mid next week.
ECDC was begun on
Friday evening and will continue up to the point
of plasma operation.
A short term schedule of planned operations can be
found at
http://www.psfc.mit.edu/cmod/operations/schedule.txt
The
new non-axisymmetric control coils were tested to their rated
current of
3000 amps last week. These coils will be used for study and
control of
locked modes and error field amplification effects during
the upcoming
campaign. Up to four coils in series were driven by a
single supply, with
current waveforms prescribed through the C-Mod
Plasma Control System (PCS)
interface and the Hybrid Control
Computer. The magnetic configuration
(toroidal phase, m/n spectrum,
and helicity) of the control field was
varied shot-to-shot using a
patch panel. Stray fields from the
igloo-mounted coils were monitored
during the tests, and the adequacy of
shielding around the pumping
station turbo-pumps was confirmed. Fields
measured by the C-Mod
magnetics diagnostics were consistent with design
calculations.
ICRF Systems
------------
The D, E, and J-Port resonant
loops have been re-assembled for
operation. The J-Port decoupling stub has been installed and tested.
D
and E-port have been connected to the transmitters and initial
testing of
the system has been completed, including low power
operation (~40 kW), and
verification of voltage and phase balance
protection. D and E-Port vacuum
conditioning will begin once the
machine bake has been completed.
Commissioning
of the control and fault protection systems is
underway in preparation for
the next run campaign.
Lower Hybrid Project
--------------------
At
MIT, work continued on bringing up rf power from the klystrons. A
body current fault had been limiting
the applied high voltage to about
42 kV.
On Friday this fault was tracked down to an arc in the dummy
load. An applied voltage of 47 kV and extracted
power of 240 kW was
then obtained (full power specification is 250
kW).
At PPPL, final preparations for shipment of the lower hybrid
launcher
were being made. Two C-Mod engineers, Bill Beck and Bob Childs,
will
visit PPPL next week to discuss final shipment details.