From:
irby@PSFC.MIT.EDU
Reply-To: IRBY@PSFC.MIT.EDU
Subject: Alcator C-Mod
Weekly Highlights
Newsgroups: sci.physics.plasma
Organization:
MIT
Alcator C-Mod Weekly Highlights
April 18, 2003
Alcator C-Mod resumed plasma
operations on Friday. Work continues
on
Lower Hybrid, ICRF, and DNB systems.
Physics
-------
Joe
Snipes has analyzed the Zeff and triangularity dependence of the
H-mode
threshold across a number of tokamaks using the ITPA
Confinement
Database. He has found that there is a strong
Zeff
dependence of the threshold with increasing threshold for
increasing
Zeff. Although
ASDEX-Upgrade reports an increase in threshold with
increasing
triangularity, there was no clear triangularity dependence
of the
threshold across the various tokamaks in the database.
Operations
----------
A
fault in the alternator motor gate drive electronics required
several days
to fix this week. The alternator was
then brought up to
full speed on Friday morning and power tests were
begun. All power
supplies and coil
systems were successfully tested. The
first plasma
attempt in the afternoon produced a 500 kA plasma. Operations will
continue next Tuesday
as we condition the vessel and regain physics
quality discharges.
A
schedule for plasma operations can be found at
http://www.psfc.mit.edu/cmod/operations/schedule.txt
Lower
Hybrid Project
--------------------
With the delivery of the
shroud/stacked waveguide assembly to MIT on
4/15, and the completion of
the rear waveguide/power splitter
assembly, PPPL has completed all the
tasks required for the LHCD
launcher part of the C-Mod LHCD Project. PPPL and MIT will now work
to install
the launcher and bring it into operation during the
fall/winter run
campaign.
At MIT, the four chassis for the Lower Hybrid Active
Controller
System electronics have been wired and assembled. Placement of the
major components in
the four rack cabinets for the Lower Hybrid Active
Controller has been
determined, and mechanical detailing has begun.
The modifications to the
top of the Low Power Microwave Rack are near
completion.
We
continue to bring klystrons into operation.
We are ready to begin
long pulse tests (each klystron will be
tested into a dummy load to
approx 200 kW for 1 s).
ICRF
Systems
------------
All transmitters are now in
operation. On Wednesday and Thursday
of
this week vacuum conditioning of the D, E, and J-Port antennas
was
begun at rf voltages of up to 30 kV.
We expect to begin rf operation
into plasmas early next week.
Diagnostic
Neutral Beam
-----------------------
The beam is ready to
operate into C-Mod plasmas. The beam power system
reliability has been
improved during the up-to-air period, and beam
performance is very
good.
We are upgrading the Java beam control program. The immediate goal
is to improve the
automation of the beam operation so that operator
intervention is not
required on every shot.
Travel and Visits
-----------------
Dmitri
Mossessian and and Amanda Hubbard participated by video
conference in the
ITPA Pedestal Group meeting in Naka, Japan and
presented results and plans
for C-Mod-AUG and C-Mod-JET dimensionless
identity experiments.
Drs.
R. Maqueda and I. Furno, LANL, were at MIT for the week. They
spent this
time re-installing and calibrating the LANL IR camera. Glen
Wurden, LANL,
continues to direct the LANL effort.