From:
"Stephen M. Wolfe" <wolfe@psfc.mit.edu>
Reply-To:
wolfe@psfc.mit.edu
Organization: MIT Plasma Science and Fusion
Center
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
June
2, 2003
Plasma operations continued at Alcator C-Mod last week, with
three run days
scheduled and completed. Runs were carried out in support
of MP#326, "High
Power ICRF Operation", MP#318, "High
Performance Operation at 5 tesla", and
MP#327, "Developing low
density EDA H-mode targets for LHCD".
Plasma runs are scheduled
to continue this week.
Operations
----------
A
total of 85 plasma discharges were produced over three run days last
week.
All tokamak systems performed well, with overall startup reliability of
about
95%. The ICRF system operated at high power (>4mW) all three days,
using
all three antennas, with peak power exceeding 6MW for short pulses.
High
radiative power fraction and elevated H/(H+D) ratio were observed,
and may
have contributed to the limitations on the pulse length of the
highest power
operation.
A fresh boronization was carried out
beginning Friday evening through Saturday
afternoon.
Physics
-------
Similar
high frequency modes in the core of RF ITB plasmas have been
identified by
Martha Redi, with the GS2 code, and by Alan Lynn (U. Texas) from
ECE
measurements. Nonlinear gyrokinetic
calculations predict an apparent
geodesic acoustic mode at 77 kHz in a low
field case at the trigger time.
The
ECE heterodyne measurements of 80 kHz were made during ITB in a
high field
case.
Operation on Friday continued experiments
begun last year on development of
low-density EDA H-mode target plasmas
for Lower Hybrid current drive, in
support of the future Advanced Tokamak
program. H-mode plasmas were produced
with Ip=600kA and sustained RF power
at the 4MW level. EDA, as evidenced by
observation of the Quasi-coherent
mode on reflectometry, BES, and fast
ECE and magnetics, was obtained with
target densities down to ~9e19/m^3, while
ELM-free H-modes, with no QC
mode, were produced at a lower target density,
~6e19/m^3. At lower RF
power the QC-mode was absent even with the 9e19/m^3
target. The
performance of these low-density H-modes was good, with H-factors
around 2
or above. ACCOME modeling of these plasmas will be carried out; we
anticipate
they will show good LH current drive efficiency.
ICRF Systems
------------
The
primary focus of the RF operations was to provide high power into plasma.
Short
pulses (~0.12 sec) at 5 MW into 1MA H-mode discharges were achieved, and
peak
powers over 6MW were briefly obtained with plasma currents up to
1.2MA.
The systems operated well into low current, higher toroidal field
discharges
that were difficult to match to during the last run campaign.
Improvements
to the demodulator circuits that detect rf power levels
and drive fault
detection circuitry resulted in better reliability of
the rf systems this
week. Up to 2.7 MW has now been coupled
through
the j-port antenna,
although more conditioning is required for full
performance
operation.
Lower Hybrid System
-------------------
High
power testing of the prototype circulator was begun this week.
Apparent
waveguide faults limited peak power to approximately 100 kW.
The fault
location has not been identified and may not be in the
circulator. We are in the process of tracking down the
source of this
fault and also a gas leak in the circulator that may
eventually limit
performance.
The PXI Interface chassis, SFOL
chassis, Logic chassis and patch panels were
installed into the LH Active
Controller racks and a temporary ethernet was run
to the rack area. Fiber optic cables were pulled into place
for
CPS and Low Power Microwave Rack; termination is still required.
The
lower hybrid launcher forward stacked waveguide completed its 150C bake
cycle
last week. New locations with
blistering and peeling were found,
resulting in a decision to disassemble
the guide and replate.
The lower hybrid grill couplers have been
successfully stripped and are now
being prepared for plating. An electrode assembly has been designed
and
fabricated at PPPL in cooperation with MIT and the vendor.
DNB
System and Diagnostics
---------------------------
DNB
performance was very good last week, with beam currents averaging 4.5
Amps
at voltages of 49.5 kV. No gas system problems have re-appeared. The computer
CRT in the cell was
changed out for a spare flat panel display.
Work
continues on fiber links between the local Russian beam camac
and the C-Mod DNB
camac (which is recorded in MdsPlus). The fiber links
are being made up from
spare and used AFOL boards.
Diagnostics
------------
The
132 GHz reflectometer channel has become operational. Iniital data look
very good. The auto power spectra show the expected specular reflection,
MHD
activity, and a broad background of density fluctuations. The coherent
scattered power, which is
an indication for the density fluctuation level
varies when the plasma
evolves and at times there is even a weak cross
correlation visible with
the 88 GHz channel.
The NSTX X-ray imaging crystal spectrometer was
installed on C-Mod
5/24.
Everything went very well. Tom
Holoman and Doug Lebrie moved
the equipment from NSTX to MIT on Friday
morning and put it on the
C-Mod platform in the afternoon. On Saturday, John Rice, Ken Hill, Doug
Lebrie
and Manfred Bitter installed the spectrometer on the horizontal
(lower-hybrid)
port and aligned the crystal. The next
steps are to install
the detector and connect the Korean PC-based data
acquisition system to
MDSplus. The spectrometer will then be ready to take
data.
Travel and Visitors
-------------------
Ken
Hill, Doug Lebrie, Brent Stratton, and Manfred Bitter (PPPL) visited to
work
on the installation of the NSTX X-ray imaging crystal spectrometer on
C-Mod.
Bob
Childs and Rui Vieira were at PPPL on 5/30 for ongoing evaluation of the
LH
launcher following the 150C bake cycle tests carried out last week.