From:
"Stephen M. Wolfe" <wolfe@psfc.mit.edu>
Reply-To:
wolfe@psfc.mit.edu
Organization: MIT Plasma Science and Fusion
Center
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
June
30, 2003
Last week was a maintenance week at Alcator C-Mod. No runs
were
scheduled. Plasma operations will resume this week.
The
C-Mod Experimental Program Committee met at MIT on Thursday, with remote
participation
from PPPL, U. Texas, and GA. Thirteen MiniProposals, most for
experiments
to be carried out during the remainder of the present campaign,
were
considered at this meeting. A tentative run schedule has been developed.
Operations
----------
No
plasma operations were scheduled. The tokamak was maintained under vacuum
and
60C bake as the engineering staff performed preventive maintenance tasks
and
worked on power system improvements.
The Netware server PC for the
Paragon interfaces to the engineering and
diagnostic PLC's was replaced
with a more reliable computer; the old server
had experienced several
crashes in recent weeks, necessitating reboots of all
of the Paragon
stations.
A second TMX (slave) supply to increase the
voltage/current available to drive
the non-axisymmetric control coils was
installed in the power room. This
includes
AC input wiring and high current DC wiring and connection at
the slave
supply, as well as control circuit wiring in both master and slave
supplies.
The PLC programming work to operate the second supply has also been
completed.
The original TMX master supply is still connected and ready for use
during
this week's operation. Some additional wiring and testing of the
master/slave
configuration into a dummy load will be required before the
combined power
supply is ready for use.
Physics
--------
At the
Monday group meeting, Robert Granetz showed results of observations of
beam
heating by the diagnostic neutral beam in low density, low current ohmic
discharges.
The beam power into the plasma is of order 100 kW, primarily in
the form
of 50 keV hydrogen ions, injected perpendicularly to the magnetic
field. This reasonably mimics the ICRF H minority
heating scheme. The
increase in
plasma total stored energy due to the DNB was roughly 1 kJ, which
is just
discernible on the EFIT calculation of stored energy. Plasmas with
locked modes generally show less efficient DNB
heating, possibly indicating
enhanced loss of fast perpendicular
ions. With the new long-pulse
DNB,
expected in early 2004, it will be possible to modulate the beam
throughout
the discharge, allowing energy confinement analysis of ohmic,
L-mode, H-mode,
ITB's, etcetera to be systemically compared in a single
discharge.
ICRF Systems
-------------
Initial
current drive phasing tests for the J-port four strap antenna were
successfully
completed. The phase control settings were determined from vacuum
measurements
and agreed well with expectations. The
J-port loops have been
reconfigured for heating phase for this week's
runs.
Operation of the 500W Kalmus amplifier on transmitter #2 was
verified to be
qualified for long pulse (5 sec) operations.
Lower
Hybrid System
-------------------
The location of the arcing in
the circulator assembly has been determined by
extensive testing to be
near the center of the circulator itself. The unit is
being crated and
will be shipped back to the vendor for evaluation and repair.
Preparations
for power testing of the lower hybrid launcher are proceeding.
All of the
rigid elbows required for the test have been received. We also
received nine out of twelve
waveguides with flanges (12' long) required for
the test. All of the
brackets for holding the waveguides have been installed
in the cell.
DNB
Systems
-----------
The DNB turbopump which failed last week
was temporarily replaced with a
spare, and the beam is operational for
this week's runs. The failed pump will
be repaired and returned to service
after the end of the present run
campaign.
Diagnostics
-----------
Work
continued on bringing up the NSTX imaging Xray Crystal Spectrometer. The
crystal was rotated slightly to
improve the centering of the argon spectrum on
the detector. The crystal was also masked down to reduce
the detector count
rates to acceptable levels. Calculations indicate that the etendu of this
spectrometer
is much higher than that of the single chord C-Mod crystal
spectrometers,
consistent with the observation of symptoms of high count rate
and
detector/electronics saturation during C-Mod discharges. Measurements
were
made to better understand the apparent high deadtime fraction of
the
signal-processing electronics at high count rates, and to assess
the
individual contributions of the TDC and the KBSI interface box to
this
deadtime. Measurements on C-Mod plasmas with this instrument will
continue
during the upcoming week's operation.
The 140 GHz
channel of the reflectometer diagnostic system needed some small
retuning
to compensate for temperature-induced frequency drifts. The 130 GHz
channel was also modified
so that it can be tuned easily to allow for
frequency drifts due to
temperature changes.
Travel and Visitors
-------------------
On
Monday, 6/23, Larry Dudek, Doug Loesser,
Rich Hawryluk, Joel Hosea,
Ned
Sauthoff, Gerd Schilling, and Skip Schoen, all from PPPL, visited
MIT for
a meeting on the Lower Hybrid Launcher. Scheduling of the
plating,
brazing, and testing activities was discussed.
Attending the
meeting from MIT were Ian Hutchinson, Earl Marmar,
Ron Parker, Miklos
Porkolab, Jim Irby, Bill Beck, Bob Childs, and Rui
Vieira.
Manfred Bitter and Ken Hill (PPPL) were at MIT this week making further
improvements to the
NSTX imaging XCS. Gerrit Kramer was at C-Mod 6/23-25
working on the
reflectometer diagnostic; he also installed his reflectometer
data
analysis program on the Linux cluster to facilitate analysis of
fluctuation
data.
E3-I: This message has been scanned for viruses and dangerous
content by UML's antivirus scanning services.