From:
"Stephen M. Wolfe" <wolfe@psfc.mit.edu>
Reply-To:
wolfe@psfc.mit.edu
Organization: MIT Plasma Science and Fusion
Center
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
Sept
29, 2003
The maintenance period at Alcator C-Mod continued last
week. Progress
continued on all systems in preparation for resumption of
tokamak operations
in early October. There was also considerable progress
on the Lower Hybrid
Project.
Operations
----------
The
vessel was subjected to a 120 degree C bake beginning on Monday and
lasting
through the weekend. Electron Cyclotron Discharge Cleaning (ECDC) in
deuterium
was carried out simultaneously with the high temperature bake.
The
alternator reassembly has been completed and the unit is expected to
return
to service this week. The machine was on turning gear over the
weekend.
Some instrumentation work remains to be completed prior to
operation.
ICRF
System
------------
Work began on tuning transmitter #4
(J-port) to 50 MHz in preparation for
plasma operation at that frequency
in October.
DNB Systems
-----------
The diagnostic
neutral beam system is being readied for resumed
operation.
Instrumentation in the LHe dewar was repaired and re-installed. The
vacuum
system is reassembled and ready for startup. A new turbopump has been
installed.
A new connector flange that provides additional instrumentation
between
the gate valve and the pump was installed.
The new 2d cxrs detector
was installed and initial alignment completed by Bill
Rowan (UT-FRC). The detector will allow the number of
spatial channels which
can be used simultaneously to increase to 40.
Lower
Hybrid System
-------------------
The Lower Hybrid launcher
work continued this week. Dielectric
constant
measurements have been completed for four new ceramic window test
samples at
the operating frequency of 4.6 GHz. The measurements result in a slight
reduction in window
thickness, and the new dimension has been passed on to
the manufacturer
for grinding.
Removal of the old windows from the first coupler
through acid etching of
the braze material has progressed slowly. Seven bricks have been removed,
nine
bricks are loose but not yet out, and the remaining eight bricks show
acid
flow past the periphery. We are
attempting to speed up removal by
purchasing baffling, acid pumps, and acid heaters/controllers in order
to
direct acid flow better, increase the acid temperature to raise the
etching
rate, and allow all remaining couplers to be etched in parallel. This is
expected to speed up this
process considerably.
Our brazing vendor has performed eight
additional braze coupon tests, six
with ceramic and two with bare
metal. These tests concentrated on the
two
alloys which had performed best in the initial investigation, Gapasil
and
Silver ABA. Preliminary
indications from a tapered gap test show good
wetting and filling. The Silver ABA seems to wet the titanium
metal better,
but also wets the alumina better, which might lead to a
greater cleanup
effort. A test
summary report is expected from the vendor by 9/29.
Work is
continuing with Bill Beck (MIT) on the concept of thinning the
coupler
outer walls to reduce mechanical stresses on the ceramic. Two
thinned-wall concepts will be braze
tested starting next week, with a total
of six to seven 3-channel
samples. The braze alloy will be chosen
after
receipt of the test summary report.
Bill is also investigating measuring
post-brazed stresses.
The
Forward Wave Guide that was successfully power-tested at MIT has been
returned
to PPPL. Positioning holes are being
reamed for final assembly, to
be followed by trial fit-up with
flanges. A final assembly procedure
is
being generated, and will be reviewed with MIT.
At MIT, work
last week centered on testing of the circulators and the reworked
water-cooled
dummy loads; improvements to these loads made by the vendor to
bring
performance up to specification include silver plating and increased
water
flow. The tests were carried out with the assistance of an engineer from
the
vendor. After some on-site modifications, both loads successfully passed
full
power, full pulse length tests. The next tests were with the circulator
terminated
into a matched load. Full power and pulse width operation was
achieved. The output was then terminated with a
shorting plate (to simulate
an arc) with the water load to Port 3 of the
circulator. Full power and full
pulse width were again achieved.
During
the last of the 5 second circulator tests, problems were encountered
with
the klystron V3 of cart 2. The output power was found to be low early in
the
pulse and then increasing in time. This behavior may be indicative of the
tube
becoming "gassy". We are considering means to remedy this
situation.
Meanwhile, the two rebuilt klystrons received earlier from CTL
are being
perpared for installation and testing.
Visitors and
Travel
-------------------
Garry McCracken visited the PSFC
Sept 25 and discussed edge physics with the
edge group as well as the
prospects for ITER.
On Wednesday of last week, Earl Marmar, Martin
Greenwald, Bruce Lipschultz
and Miklos Porkolab travelled to Germantown to
meet with OFES staff.
Discussions centered on recent research highlights
and plans for C-Mod.
Attending from DoE were John Willis, Rostom Dagazian,
Erol Oktay, Curt
Bolton, T.V. George, Steve Eckstrand and Arnold
Kritz.
Catherine Fiore, Dimitri Mossessian, Amanda Hubbard, Miklos
Porkolab, Darren
Ernst and Jerry Hughes (MIT), and Perry Phillips, Alan
Lynn, and Matt Sampsell
(UT-FRC) attended the 9th Annual IAEA TM on H-Mode
Physics and Transport
Barriers 9/24-9/26 in San Diego. Work was presented on control of ITBs
in
Alcator C-Mod (Fiore), and the role of TEMs and neoclassical transport
in
Alcator C-Mod ITBs (Ernst) .
C-Mod/DIIID/ JET dimensionless scaling results
for the edge
pedestal were reported by D. Mossessian and the role of plasma
and neutral
transport in the edge pedestal in Alcator C-Mod was explored by
J.
Hughes. A. Hubbard presented her work
on local threshold conditions and
the fast transition dynamics of L-H mode
transitions in Alcator
C-Mod. Phillips, Lynn and Sampsell presented
posters on "Observations of Core
Modes during RF-Generated Internal
Transport Barriers in Alcator C-Mod" and
"Measurements of the
Quasi-Coherent Mode on Alcator C-Mod"
E3-I: This message has been scanned for
viruses and dangerous content by UML's antivirus scanning services.