From:
"Stephen M. Wolfe" <wolfe@psfc.mit.edu>
Subject: Alcator
C-Mod Weekly Highlights
Newsgroups: sci.physics.plasma
Alcator C-Mod Weekly
Highlights
Oct 27,
2003
Plasma startup and conditioning operation continued at Alcator
C-Mod last
week. Four run days were scheduled and completed. A total of 60
plasmas were
produced with a startup reliability of 80%. Diagnostic
systems continue to be
brought online, and ICRF systems are being
conditioned to high power. Progress
continued on the Lower Hybrid System.
No
runs are scheduled this week, as most of the physics staff is
participating
in the 45th annual meeting of the APS Division of Plasma
Physics in
Albuquerque, New Mexico.
Operations
----------
The
run on Tuesday had to be stopped early when a monitor in the alternator
indicated
a low helium purity. Helium is used to reduce windage losses in the
alternator.
On Wednesday morning, the problem was tracked down to an air leak
in the
gas handling system. Once this was
fixed, the helium purity stayed very
high the rest of the week (~
99%).
The chopper power supply used for fast vertical position
control tripped
during a shot near the end of the run on Thursday
afternoon. The supply was
repaired, tested and returned to service Friday
morning.
Machine condition continued to improve through the week.
The H/D ratio is
presently at the 10-15% level.
Experiments to
quantify the amount of gas pumped by the vessel wall under
different
conditions are being carried out during this phase of C-Mod
operation. For
these experiments, the gate valve to torus pumping system is
left closed
during and following the discharge, and the pressure rise
monitored for up
to ten minutes. The difference between the total fueling
during the shot
and that released from the wall between shots
determines the increment to
the wall inventory. These experiments are part of
a collaborative effort
with Dennis Whyte (U. Wisc.).
Physics
--------
Robert
Granetz presented results of orbit loss calculations of 50 keV
deuterons
for the deuterium DNB run last year.
The orbit code uses a
Runge-Kutta package to solve for the Lorentz
motion of the beam ions in the
EFIT-derived poloidal and toroidal fields.
The results show that there are no
first-orbit losses of beam particles,
except for those born within ~1 cm of
the plasma edge. Pitch angle scattering can eventually cause
the loss of some
of the beam particles, but on this timescale they lose
enough energy to reduce
their fusion neutron cross-section significantly,
so this doesn't affect the
D-D neutron rate significantly.
ICRF
System
----------
Conditioning of the antennas continued last
week. We have achieved up to 5
MW total power from all antennas for pulses
up to 100 msec. D and E-port
antennas
have achieved 1.5 MW each simultaneously.
J-port has achieved 2 MW
for 0.2 sec and is behind the other
antennas in terms of conditioning.
J-port
has had less operating time due to the change of frequency
from 50 to 78 MHz
completed last week.
DNB Systems
-----------
The
DNB was operated in conjunction with C-Mod operation for most plasma
discharges.
The
arc current slope-correction circuit has been bench tested and installed.
Final
testing will be completed early next week.
Lower Hybrid System
-------------------
Both
rebuilt klystrons were successfully tested up to 46kV and 230kW for short
pulses.
Further conditioning is required to bring up the pulse length.
A
teleconference on the status of the Lower Hybrid launcher was held with
PPPL
10/22. Task updates were discussed and
several issues were resolved.
All four couplers, which were undergoing a
final cleanup procedure at
the vendor to prepare them for brazing, are now
back in house at PPPL
for inspection.
Travel and Visitors
--------------------
Stewart
Zweben (PPPL) worked with Princeton Scientific Instruments to prepare the
PSI-5
camera for delivery to C-Mod next week.
This camera captures 300
frames at up to 250,000 frames/sec, and
will be used for the Gas Puff
Imaging diagnostic as well as others.
Manfred
Bitter and Ken Hill continued to carry out experiments on C-Mod using
the
improved high resolution X-ray diagnostic from NSTX. Good spectra were
obtained
during ohmic operation, but the signal/noise was degraded during high
power
RF heating.
Marco Valisa from RFX completed his visit to work with
the Diagnostic Neutral
Beam, which is on loan to C-Mod from the RFX Group
in Padova. During his stay
he carried out several experiments to
characterize the beam operation and
associated diagnostics, while becoming
familiar with operation of the
beam.
E3-I: This message has been scanned for
viruses and dangerous content by UML's antivirus scanning services.