From:
"Stephen M. Wolfe" <wolfe@psfc.mit.edu>
Reply-To:
wolfe@psfc.mit.edu
Organization: MIT Plasma Science and Fusion
Center
Subject: Alcator C-Mod Weekly Highlights
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
Nov
10, 2003
Plasma operations resumed at Alcator C-Mod last week, after
a one-week hiatus
for the APS Division of Plasma Physics Meeting. Four run
days were scheduled
and three were completed. A total of 49 discharges
were produced, with a
startup reliability of 56%. The first boronization
of the campaign was carried
out on Thursday evening. Experiments were
conducted in support of the RF and
Edge/Divertor topical science areas.
The ICRF power into plasma was increased
to 5.2MW for 0.7 sec and 6MW for
.45 sec. Work also continued on the lower
hybrid system development.
Plasma
operations are scheduled to continue this week.
Operations
----------
Plasma
runs were carried out Tuesday, Thursday and Friday; the scheduled run
on
Wednesday was cancelled in order to investigate a ground fault indication
on
the alternator rotor. The fault was cleared and, following consultation
with
the manufacturer, operation resumed on Thursday. In addition to continued
machine
conditioning, especially of the strike point surfaces for the upper
null
configuration, two physics experiments were carried out. The RF group
completed
experiments characterizing the effect of a pre-matching network on
the
D-port antenna, as discussed below, and characterization of wall-pumping
and
gas release continued.
Following Thursday's run, a fresh
boronization was carried out, using 140 psi
of B2D6 resulting in an
average deposition thickness of 2048A. The H/(H+D)
ratio on Friday was
down to 3 or 4% and the carbon II light was down by a
factor of 3 or 4,
indicative of a good boronization. The startup
reproducibility on Friday
was also low (under 50%), which is also typical of
the first run following
boronization.
Physics
--------
The amount of
gas retained by the walls after each shot was monitored
throughout the week,
with the goals of understanding what conditions affect
the wall pumping,
assessing the wall H/D ratio and its relation to that in the
plasma, and
determining the effect of boronization.
The configuration was
varied from upper to lower single null, and
RF power from 0 to 6MW. In
addition, a series of discharges on Thursday
were run with helium majority
rather than deuterium; for these cases the
hydrogenic content of the discharge
is determined only by the wall. As
expected, helium operation also tends to
degas the walls. In a series of
discharges where the RF was first on, then
off, and then back on, the H/D
lowered during the RF off discharge and the
amount of gas required to
maintain the discharge increased relative to the RF
case. This indicates
that the RF is leading to more gas in the discharge,
possibly due to
recycling effects or heating of surfaces.
ICRF System
-----------
Further
power conditioning of the antennas has been accomplished. New high
power ICRF discharges were
achieved: 5.2 MW for 0.7 sec without fault and 6 MW
with single trip for
0.46 sec.
Quarter wavelength pre-matching transformers have been
added to the D-Port
antenna transmission line system. After proper consideration of the
reactive
component of the plasma loading was included in the design, a
large reduction
in the reflection coefficient as seen on the transmitter
side of the
transformers was found (rho from 0.75 to 0.55). A 10 kV reduction in rf
voltages in
other matching components was also seen.
These results suggest that
pre-matching can be successfully used to limit the
voltage in the phase
shifter-stub tuner matching elements.
Furthermore, we
can limit the range of reflection coefficients that
an active matching network
needs to cover.
DNB System
----------
Early
in the week a 12 V supply in the DNB rack malfunctioned. A replacement
supply was installed
after the end of Tuesday's run.
Although C-Mod did not
run on Wednesday, the DNB was fired
throughout the day for conditioning
purposes. A minor problem with an intermittent trigger cable was
fixed.
During plasma operation on Thursday and Friday the beam was fired
on nearly
all shots. Thursday's
run provided useful BES data to compare helium and
deuterium plasmas. For the last shot on Thursday, the MSE polarizer
was
installed and pitch angle data was obtained during a period of very
long
sawteeth. The DNB continued
to run well throughout Friday, with beam ion
current at 5 amps on many
shots.
Lower Hybrid System
-------------------
The
front end couplers are presently being refurbished at PPPL. All bricks
and residual brazing alloy
have been removed, and machining to reduce wall
thickness and lower
brazing stresses is under way. Roughly
half of the new
ceramic windows have been received following edge metallizing,
the remaining
are due next week.
The greater part of prototype braze testing has been
completed.
The
forward waveguide part of the launcher has now been completely
reassembled
at PPPL, the shroud has been welded, and vacuum leak checking
is in progress.
Mechanical distortion due to the welding has been reduced
from the first
assembly.
The Coupler Protection System (CPS)
design is nearly finalized, and PC board
layouts for the I/O boards have
been completed.
Travel and Visitors
--------------------
Joe
Snipes attended the Active MHD Control Workshop in Austin, Texas from 3 -
5
November and presented results from Active MHD Experiments on C-Mod.
Perry
Phillips of UT-FRC was on-site for several days to start repairs for the
FRC
ECE radiometer. At present, it appears
that the local oscillator for 16
of the 32 channels has failed. The LO has been sent to the manufacturer
for
testing. The radiometer will
remain in service with 16 core channels.
During the week prior to
the APS-DPP meeting, Matt Sampsell prepared the BES
system for operation
by calibrating the spectrometer, positioning the
fibers/views, and tuning
the bandpass filters.
Manfred Bitter, Ken Hill and Sang Gon Lee
(Korea Basic Science Institute)
were at MIT this week, installing a new
detector for the X-ray crystal
spectrometer. Helium-like Argon spectra were measured during the runs,
and
will continue in the coming week. Analysis of the data is
ongoing.
E3-I: This message has been scanned for viruses and dangerous
content by UML's antivirus scanning services.