From:
"Stephen M. Wolfe" <wolfe@psfc.mit.edu>
Reply-To:
wolfe@psfc.mit.edu
Organization: MIT Plasma Science and Fusion
Center
Subject: Alcator C-Mod Weekly HIghlights
Newsgroups:
sci.physics.plasma
Alcator
C-Mod Weekly Highlights
Dec
15, 2003
Research operations continued at Alcator C-Mod last week.
Four run days were
scheduled and completed. Experiments were carried out
in support of RF
Physics, Burning Plasma Support and Advanced Tokamak
research programs.
Progress also continued on the Lower Hybrid
Project.
Plasma operations are planned to continue this week.
Operations
----------
Four
days of experimental operation were carried out. A total of 118 plasma
discharges
were produced with a startup reliability of 93%. In general, all
tokamak
systems performed well this week, resulting in an average of nearly 30
successful
plasmas per day, the highest production of the present
campaign. Computer
and data system reliability were considerably improved,
although a server
crash on Thursday did result in about a one hour delay.
Runs on
Tuesday and Wednesday were devoted to MP#376, "Study of the
Efficiency
of ICRF Minority Heating and Investigation of the Cause of Low
H-mode Plasma
Performance".
Scans of plasma shape, antenna-plasma gap, density, current,
and
power were carried out in an effort to identify parameters which impact
ICRF
efficiency and plasma performance in H-mode discharges. Comparisons were
also
made between the J-port and D- and E-port antennas in H-mode. All the
experiments
were carried out using H minority heating in either D or He
majority
plasmas at 5.2-5.4 tesla (f=78-80.5 MHz).
The best plasma
performance during these experiments, carried out
on the second and third day
following boronization, was among the best of
the past several years, with a
number of cases achieving stored energy
above 200kJ. The plasma response was
fairly insensitive to outer gap and
upper and lower triangularity. In
addition
the plasma confinement improved with plasma current. The increase in
stored energy was nearly linear with RF
power in H-mode. Degradation in
performance during a given run day was
observed, as well as some degradation
from day to day, as indicated by
comparison of fiducial discharges with rf
power up to 5MW.
Thursday's
run was the first day devoted to MP#377, "Energy confinement in
double-null
discharges". This MP forms part of the experimental program in
support
of our Level 1 Milestone SC6-1b, "Compare energy confinement, H-mode
threshold
and divertor particle dynamics in SN, DN and inner-wall limited
discharges
in Alcator C-Mod". Dale Meade (PPPL) was at MIT to serve as
co-Session
Leader for this run. The experiments concentrated on comparison of
double
and near-double null discharges at moderate density (n/n_G~0.4) and
currents
of 1 and 1.2MA (q95~4.1,3.4) with lower single null plasmas at the
same
parameters; ICRF power was ~4.5MW on all shots. A small (~10%)
improvement
in confinement was observed in the DN cases, especially at the
higher
current. In all cases on this day we obtained multiple H-modes, with
apparent
increases in radiated power during the H-phase. There were
indications
that the effectiveness of the boronization was substantially
reduced
relative to earlier in the week.
Friday's run was in support of
MP#374, "ITB dependence on triangularity". The
purpose of this
experiment is to explore the influence of the plasma
triangularity on the
ITB quality, and specifically to see if obtaining an ITB
is easier, and if
higher densities and better confinement can be achieved by
varying the
shape. The ITB's were formed by use of off-axis (high-field side)
ICRF
heating with Bt=4.5T, using up to 3MW of RF power. As in previous
experiments
of this sort, the ITB evolves from an EDA H-mode and is
characterized by a
strong peaking of the density and pressure profiles. Good
ITB discharges
were obtained over a range of upper and lower triangularity in
lower SN
discharges, and also in well-balanced DN discharges. We were able to
obtain
ITBs with up to 3MW of ICRF power in double null operation. Access to
ITB's
appeared to be easier with larger values of lower triangularity
(delta_L),
but further analysis of the data is required. In contrast to the
higher
power experiments of the previous day, and to the previous run devoted
to
this ITB MP, radiated power was not excessive, and the EDA H-mode targets
were
readily achieved.
ICRF System
-----------
The
ICRF Systems were employed for plasma heating in all four runs this week.
Early
in the week, FMIT#3 required additional tuning due to high FPA screen
current. Optimizing the tune allowed operation to
resume up to nominal full
power into plasma (1.5 MW). On Thursday, the
FMIT#2 deionized water exchange
valve stuck open resulting in a low level
alarm in the C-Mod main DI water.
We will install additional monitoring to
ensure an overflow is detected, and
this valve will be replaced.
In
comparative experiments it was noted that, although the plasma response
in
L-mode was similar for the D&E-port and J-port antennas, an
increase in the
rate of impurity accumulation with the J antenna was
identified in H-mode.
These experiments were done at higher plasma current
which also increased the
impurity confinement time. With the increased impurity confinement
time,
small differences in the impurity production rate were more
obvious. Further
investigation of
the phase dependence of the impurity production rate need to
be
investigated to provide some data on whether this difference is
attributable
to basic antenna design or antenna phasing (J-port is
[0,pi,pi,0] compared to
D and E-port which are [0,pi]).
Clean
RF operation required lowering the F-side neutral pressure to
<0.3mTorr,
which imposes a restriction on the maximum density of the
target discharge.
Operation has been achieved at higher neutral pressures
but the antennas are
more likely to fault, particularly J-port.
During
an upward-biassed (SSEP>0) near-double null discharge on 12/11, a 65
msec
sawtooth period was observed .
"Monster" sawteeth (period >50 msec) have
recently
been observed on several other upper single null discharges. In this
case a 5.6 keV central electron
temperature was obtained. A phase scan
with
the J-port antenna may give information on what is causing the long
period
sawteeth.
DNB Systems
------------
The
DNB is now back in full operation. Beam performance this week has been
the
best since this beam system was installed. The beam has been very
reliable and
is delivering 5A, 50 ms, 48 kV beam shots with less than 10%
change in beam
current during the shot.
The spurious faults that had reduced the reliability
of the high
voltage beam systems have been eliminated.
Changes included
improved high voltage power supply grounds, repair
of one non-bonded fault
indication wire, and improvement of power supply
filtering in the inverter
modules.
Lower Hybrid System
-------------------
MIT
Engineers carried out a final inspection of the Forward Waveguide
assembly
at PPPL on Wednesday. The
inspection went well, low-power RF testing has now
been completed, and
final fitup to the port extension is in progress.
Travel and
Visitors
-------------------
David Mikkelsen (PPPL) was at MIT
this week learning from Nils Basse about the
C-Mod reflectometer systems
and their data analysis procedures.
Discussions
with Nils, Steve Wolfe and Steve Scott produced several
good leads for
developing experiments in C-Mod to probe turbulent
transport.
Dale Meade was at MIT 12/10-11 and served as co-Session
Leader during
Thursday's experiment.
Gerd Schilling was at MIT 12/9-12 to
participate in all ICRF-heated
experiments.
Bill Beck, Bob Childs, and Rui Vieira visited PPPL last
week for an
inspection of the lower hybrid forward waveguide.
E3-I: This message has been scanned for
viruses and dangerous content by UML's antivirus scanning services.