Date:
Mon, 12 Jan 2004 17:38:16 -0500
From: "Stephen M. Wolfe"
<wolfe@psfc.mit.edu>
Reply-To: wolfe@psfc.mit.edu
Organization:
MIT Plasma Science and Fusion Center
Subject: Alcator C-Mod Weekly
Highlights
Alcator
C-Mod Weekly Highlights
Jan
12, 2004
Plasma operations resumed on Alcator C-Mod last week. Four
run days were
scheduled and three completed; Friday's run was cancelled
due to a fault in
one of the ICRF Transmitters. Progress continued on the
Lower Hybrid project.
Operations
----------
Plasma
runs were carried out Tuesday-Thursday last week in support of
experiments
in the Transport and RF Physics programs. A total of 71 discharges
were
produced with a startup reliability of ~85%. A fresh boronization was
carried
out over Tuesday night.
Tuesday's run completed MP#363 on LH
Threshold physics in Single- and
Double-null and Limited equilibria. The
main thrust of this day's experiments
was to determine threshold powers
and corresponding plasma parameters in the
Inner Wall limited
configuration. This configuration proved to have an
extremely high L-H
power threshold. ICRF power up to 5.8MW was applied in a
series of limited
discharges. Of these, only one achieved H-mode; assuming 80
percent ICRF
absorption and adding ohmic power, Ptot was 5.0 MW, as compared
to 1.3 MW
at threshold in LSN (ie 3.8 times higher); this is more than in
either DN
or USN configurations. In contrast, equilibria limited near the
bottom of
the inner wall, at the "nose" plate, transitioned to H-mode at
essentially
the same power as the lower null discharges. These results
contribute to
the level 1 JOULE milestone SC6-1b, "Compare energy confinement,
H-mode
thresholds, and divertor particle dynamics in Alcator C-Mod
discharges".
Prior
to boronization on Tuesday night, a series of low density plasma
discharges
were run to "unload" the walls, to evaluate the effect on the
boronization
process. A total of 120psi of diborane was used (a "medium"
level),
followed by several hours of ECDC in helium. Subsequent recovery shots
and
RF antenna re-conditioning proceeded rapidly on Wednesday. The remainder
of
the run on Wednesday and the run on Thursday were devoted to continuation
of
MP#376 on ICRF Heating efficiency and performance. Variations in density,
and
midplane neutral pressure were performed on Wednesday, with higher plasma
performance
observed at the lower range of neutral pressure. A scan of the
outer gap
on Thursday indicated the dependence of heating on this parameter
was
insignificant, as had been previously observed. PEP mode shots were
obtained
using Li pellet injection, with similar stored energy to the
gas-fueled
shots. Finally, strongly radiating (near 100%) discharges were
produced by
puffing of Argon and Neon, to check efficiency of RF heating and
calibration
of spectroscopic and bolometric measurements.
Physics
--------
During
recent LSN, DN, and USN discharges, chirping modes with a frequency
between
200 and 400 kHz and k=1-2 cm^-1 have been observed by the Phase
Contrast
Imaging (PCI) diagnostic. The modes are
most intense following a
sawtooth crash and multiple modes appear during
the sawtooth evolution. These
modes
appear to be suppressed by the sawtooth precursor. During monster
sawteeth, multiple chirping modes are
observed between 200-300 kHz. The
identification
of these modes is still under analysis.
ICRF System
-----------
On
Wednesday, the FMIT#1 transmitter (D-port) experienced a fault of the
final
power amplifier (FPA) tube. This tube had ~2500 filament hours,
which is
beyond its estimated mean lifetime. A spare tube is being readied
and will be
installed this week.
On Friday morning, a control
system fault of the 13.8kV breaker for FMIT#4 led
to damage of some
components in the soft start and crowbar cabinets. Required
repairs and impact on operations are being
evaluated.
Lower Hybrid System
-------------------
Installation
of the circulators has begun. Three of the twelve units have now
been
installed.
Following measurements of the fitup between the forward
and rear waveguide
assemblies, the forward waveguide was shipped to a PPPL
vendor to complete
machining to assure proper gasket compression. Final
assembly and tests are
expected to begin at MIT by the end of the
month.
Travel and Visitors
--------------------
Ron
Bravenec (UT-FRC) spent the week at MIT to setup the BES diagnostic for
beam
width measurements and for poloidal wave number and phase velocity
measurements
of the QC mode. This involved moving
fibers and acquiring new
calibration data.
Doug Loesser (PPPL)
was at MIT 1/8 to review the Lower Hybrid Launcher
assembly schedule and
for final fitup measurements of the waveguide
assemblies. Joe Frangipani
and Dave Miller were also at MIT 1/8-9 to assist
with the waveguide
fit-up, measurements and transport back to the PPPL
vendor.
Dr.
Maxim Umansky (LLNL) visited the PSFC for January 8 and 9. Dr. Umansky
presented
a seminar on the BOUT edge turbulence simulation code and had
detailed
discussions with C-Mod scientists, Miklos Porkolab, Peter Catto, Jim
Terry,
Brian LaBombard, Olaf Grulke, Martin Greenwald, and Bruce Lipschultz
regarding
comparison of future BOUT simulations of C-Mod with our extensive
edge
turbulence data. We are also planning
C-Mod experiments that would
benchmark certain crucial aspects of
BOUT.
E3-I: This message has been scanned for viruses and dangerous
content by UML's antivirus scanning services.